Company: HUACONN ELECTRONICS LIMITED
PCN No.: PCN-001-2025
Issue Date: October 10, 2025
Dear Valued Customers and Partners,
Thank you for your continued support and trust in Dongguan Huaconn Electronics Co., Ltd.
To support our long-term business growth, improve our working environment, expand production capacity, and further enhance product quality and service capability, we are pleased to inform you that our company will relocate to a new manufacturing facility.
This relocation is a strategic upgrade of our operations and marks an important milestone in our development. The new facility offers a larger production area, improved infrastructure, and a more optimized manufacturing environment, enabling us to better meet customer requirements and deliver higher-value products and services.
1. Relocation Details
Original Production Address:
No.11 Wangjiao Road,Hengtang,Tangxia,
523713,Dongguan China
New Production Address:
No. 2, Luyi 1st Road, Tangxia Town,
Dongguan City, Guangdong, 523718 China
Relocation Schedule:
- Relocation starts: December 1, 2025
- Relocation completed: December 31, 2025
- All company products, including existing and newly developed products, are covered under this relocation.
2. Impact Assessment
2.1 Product Quality & Compliance
Production processes, equipment, raw materials, and quality standards will remain unchanged.
Product quality consistency will be maintained, fully complying with customer and regulatory requirements.
The new factory has passed relevant management system certifications such as ISO9001 and ISO14001.
There will be no impact on product performance, reliability, or delivery schedules.
2.2 Customer Impact
Customer order delivery plans will remain unaffected, ensuring continuity of supply.
If required, trial production samples can be provided for customer verification and approval.
All contractual shipping addresses will be updated to the new factory location.
3. Relocation Implementation Plan
|
Phase |
Description |
Start Date |
End Date |
|
Phase 1 |
Relocation planning |
Sep 1, 2025 |
Oct 9, 2025 |
|
Phase 2 |
Preparation stage |
Oct 10, 2025 |
Nov 8, 2025 |
|
Phase 3 |
Equipment & material relocation |
Nov 9, 2025 |
Nov 30, 2025 |
|
Phase 4 |
Production transfer & trial run |
Dec 1, 2025 |
Dec 31, 2025 |
4. Quality Assurance Measures
The first three production batches at the new factory will undergo 100% inspection, with results compared against historical production data to ensure full consistency.
5. Supply Chain Assurance
Key suppliers have been audited and approved for the new factory logistics routes to ensure stable and continuous raw material supply.
6. Confirmation & Contact
Please confirm receipt of this notice within 5 working days.
If you require additional support or have any questions, feel free to contact us.